Transforming Walmanyjun Cable Beach Foreshore into a globally recognised waterfront precinct


Project Timeline

April 2025
Expected start of Stage 2. Activities include: New plaza corridor, Amphitheatre realignment with better ocean views, Additional lawn area, Facilities for small and larger-scale concerts and events, Shade structures and Realignment of vehicle access road
April 2025
Stage B1 Activities due for completion
March 2025
Tender awarded for Stage 2 of the project with the appointment of CMA Contracting Pty Ltd
January 2025
Shire of Broome receives a $9 million of funding from the WA State Government for Stage 2
July 2024
Shire of Broome secures a $1.66m CoastWA grant for northern end of Cable Beach to be incorporated into Stage 2
May 2024
The Shire of Broome receives a $26.3 million Federal Government Regional Precincts and Partnerships Program (rPPP) grant for Stage 2
April 2024
Stage B1 Activities commended and include: Coastal protection measures, New free-standing vehicle access ramp at the Surf Club, New free-standing southern and central beach access stairs, Youth Hub and Trail Head Park Entrance, Art and Interpretation. Completion Expected: April 2025
September 2023
Stage A1 Construction commences. Activities include: Main entrance roundabout upgrades, Carpark resurfacing and Drainage Upgrades
December 2022 - March 2023
Tender Documentation for Stage 1
June-December 2022
Detailed design delivery
June 2022
Detailed design commences
March 2023
Community Engagement Sessions on Thursday 9 March at Paspaley Plaza and Saturday 11 March at Boulevard
June 2022
Concept detailed design 100% complete
March 2022
Community Info Display at Broome Library and Broome Boulevard
March 2022
Community Picnic at Cable Beach Foreshore
March 2022
Open Community Meeting at Shire Offices
March 2022
Community Information Session for Arts & Events, for Broome business owners and traders and for Environment groups
March 2022
Walmanyjun Cable Beach Traders Community and Stakeholder Reference Group Meeting